Reduction of lead time through curtailment of cycle time of a supplier-a case example
Citation
Raktim Dasgupta, Arup Ranjan Mukhopadhyay, Sadhan Kumar Ghosh "Reduction of lead time through curtailment of cycle time of a supplier-a case example", International Journal of Engineering Trends and Technology (IJETT), V54(4),233-251 December 2017. ISSN:2231-5381. www.ijettjournal.org. published by seventh sense research group
Abstract
This study demonstrates the methodology for reduction of cycle time in the finishing department of a manufacturing company in India. The DMAIC path of lean sigma has been followed. The process performance has been assessed through summary statistics, value stream mapping, PERT technique and sigma rating. Action plans to reduce cycle time have been chalked out through process FMEA. The application of Gnatt chart has helped effectively to reduce the replacement time of rejected material. The extent of improvement in cycle time is found to be 121 days to 69 days for Bitumen coated ductile iron pipes, and 129 days to 78 days for FBE coated ductile iron pipes. This paper will be valuable to many practitioners and researchers of lean sigma for understanding the systematic structured application of quality management tools in a real life situation through appropriate quantification.
Reference
[1] AIAG “Potential failure mode and effect analysis”,4thed, Automotive industry action group,2008.
[2] A. Muri , “Lean Six Sigma way”, Mc Graw-Hill, New York,2006.
[3] C. Sanjeevy, and C. Thomas, “ Use and application of optimizing selective inventory control technique of spares for a chemical processing plant”, International journal of design and manufacturing technology,VOL.5,NO.3,PP:86-97,2014.
[4] D.G. Malcolm , J.H. Roseboom, C.E. Clark, and W. Fazar, “Application of a technique for research and development program evaluation”, Oper.Res,Vol.7,No.5,pp:646-669,1959.
[5] F. M. Gryna, R.C.H. Chuha, and J. Defeo , “Juran’s Quality planning and Analysis for enterprise quality”, 2nd Ed, Tata Mc Graw-Hill, New Delhi,2007.
[6] H. Taha, “ Operation Research”,Pearson International 8th Ed, India,2006.
[7] J. Mortimer , “ Just-in-Time: An Executive Briefing”, Kempston, Bedford, UK: IFS Ltd,1986.
[8] J.M. James, “Gantt charts: a centenary appreciation” , Eur.j.oper.Res, Vol.149,No.2,pp:430-437,2003.
[9] J. Rajaniemi , “Lead Time Terminology in Manufacturing”, available at: WWW.Leadtimes.Org. accessed 15th July, 2015.
[10] J. Sharma , Operation Research Theory and Application,4th ed, Macmillan Publishers India Limited, 2009.
[11] M. Harry, P. Mann, O. Hodgins ,C. Lacke, and R. Hulbert, “Practitioner’s guide for statistics and lean six sigma for process improvements”, Hoboken, New jersey, A John Wiley & Sons, Inc, Publication,2010.
[12] N. Wilhelmsson , and E. Dahlberg, “Lead Time Analysis and Reduction at Alfa Laval Dc Lund”, A Case Study for the Industrial Management and Logistic, Lund University,2012.
[13] Process flow diagram, Value stream mapping, retrieved from http://sixsigmastudyguide.com/lean-concepts-study-guide/, http://sixsigmastudyguide.com/value-stream-mapping/ .accessed on 30 July 2016.
[14] R. Mhetre, and R.Dhake, “Using Failure Mode Analysis in a Precision Sheet Metal Part Manufacturing Company”, Journal of Applied Science and Engineering Research, Vol.1,No.2,pp:302-311,2012.
[15] S. Furterer,A. K. Elshennawy, “Implementation of TQM and lean six sigma tools in local government: a frame work and a case study”, Total Quality Management & Business Excellence,Vol.16, No.10,pp:1179-1191,2007.
[16] S. Gupta, “What is the best type of bitumen for waterproofing the foundation how many layers of bitumen is enough to provide protection?”,2016. retrieved fromhttps://www.quora.com/What-is-the-best-type-of-bitumen-for-waterproofing-the-foundation-how-many-layers-of-bitumen-is-enough-to-provide-protection ,accessed 26th june 2016.
[17] S. Hsien, “Failure Mode and Effect Analysis an Integrated Approach for Product and Process Control”, International Journal of Quality and ReliabilityManagement,Vol.13,No.5,pp:8-26,1996.
[18] S. Kmenta,and K. Ishii “Scenario-based failure modes and effects analysis using expected cost”, J.Mech.Des,Vol.126, No.6, pp:1027,2004.
[19] S.Shingo, “ A Revolution in Manufacturing”, USA, The SMED system Productivity Press,1985.
[20] S. Shingo, “A Study of Toyota Production System from an Industrial Engineering View-Point”, USA, Productivity Press,1989.
[21] W. E. Deming, “Out of the Crisis, Quality, productivity and Competitive Position”, Productivity & Quality Publishing Private Limited,1st Ed, Madras,1993.
[22] Wikipedia references: Fusion bond epoxy coating process, retrieved from https://en.wikipedia.org/wiki/Fusion_bonded_epoxy_coating#External_links accessed on 25th may 2016 Ductile iron pipe, retrieved from https://en.wikipedia.org/wiki/Ductile_iron_pipe accessed on 25th may 2016.
[23] Z. He, Y. Deng, M.Zhang, X. Zu, and J.Antony, “An empirical investigation of the relationship between six sigma practices and organizational innovation”, Total Quality Management & Business Excellence, (online)2015.
[24] Z. Mallick , S. Ahmad ,and L.Bisht, “Barriers and enablers in implementation of lean six sigma in Indian manufacturing industry”, International journal of advanced research and management,Vol. 3,No.1,pp:11-19,2012.
Keywords
Lead time, PFMEA, PERT, Gnatt chart, sigma rating, value stream mapping.