A review of Permanent control of embankment dam stability during construction
Citation
Abolfazl Kianpouri, Masoud dehghani"A review of Permanent control of embankment dam stability during construction", International Journal of Engineering Trends and Technology (IJETT), V22(7),296-299 April 2015. ISSN:2231-5381. www.ijettjournal.org. published by seventh sense research group
Abstract
Permanent control of embankment dam stability
during construction, the first impounding and also during
utilization of the project, is a significant issue. Instrumentation of
such dams which monitor the dam behavior, plays an important
role in the dam stability. Regarding that an earth dam is a
continuous structure with non-linear behavior, finite element
method and appropriate soil modeling could be employed for
non-linear analysis.Deformation of an earth dam is a complex
process in which one should consider thenonlinear behaviour of
the construction material, interaction between the structure
andthe underlying soil and rock strata, influence of water load
on the structure and on thefoundation bedrock, and the effects of
water saturation. Also the deformations and stresses that develop
in embankment dams duringthe construction phase are
presented and illustrated by analyzing the behaviour of oneof the
most important structures of the La Grande Hydroelectric
Complex.
References
1. Jing L, Liang H, Li Y, Liu C. Characteristics and factors that
influenced damage to dams in the M s 8.0 Wenchuan earthquake.
EarthqEngEngVib2011;10:349–58.
2. Gu G, Shen C, Qin W. Earthquake engineering for earthrock dams.
Beijing: China Water & Power Press; 2009.
3. Sarma SK. Stability analysis of embankments and slopes.
Geotechnique 1973;23:423–33.
4. Sarma SK. Seismic stability of earth dams and embankments.
Geotechnique 1975;25:743–61.
5. Spencer E. Earth slopes subjected to lateral acceleration. J
GeotechGeoenvironEng 1978;104:1489–500.
6. Baker R, Shukha R, Operstein V, Frydman S. Stability charts for
pseudo-static slope stability analysis. Soil DynEarthqEng
2006;26:813–23.
7. Leshchinsky D, San K-C. Pseudo-static seismic stability of slopes:
design charts. J GeotechEngDiv 1994;120:1514–32.
8. VassilisGikas, Michael Sakellariou. Settlement analysis of the
Mornos earth dam (Greece): Evidence from numerical modeling
and geodetic monitoring. Engineering Structures 30 (2008) 3074–
3081.
9. Yong-Seong Kim, Min-Woo Seo, Chung-Won Lee, Gi-Chun Kang.
Deformation characteristics during construction and after
impoundment of the CFRD-type Daegok Dam, Korea.
Engineering Geology 178 (2014) 1–14.
10. Bin Xu, Degao Zou, Huabei Liu. Three-dimensional simulation of
the construction process of the Zipingpu concrete face rockfill dam
based on a generalized plasticity model. Computers and
Geotechnics 43 (2012) 143–154.
11. SZOSTAK-CHRZANOWSKI A., CHRZANOWSKI A. and
MASSIERA M. 2003. Use of Geodetic Monitoring Measurements
in Solving Geomechanical Problems in Structural and Mining
Engineering. Proceedings, FIG 11-th International Symposium on
Deformation Measurements, Santorini Island, Greece (in print).
12. SZOSTAK-CHRZANOWSKI A., MASSIERA M.,
CHRZANOWSKI A., LE HOAN F. 2002. Verification of design
parameters of large earthen dams during the filling process.
Proceedings, 2nd Canadian Specialty Conference on Computer
Applications in Geotechnique, April 28.30, Winnipeg, MB: 54.59.
13. Société d`énergie de la Baie James. 1987. The La Grande Riviere
Hydroelectric Complex, Phase One Development, Montréal,
Québec, 467.
14. PARÉ J.J., BONCOMPAIN B., KONRAD J.M., VERMA N. S.
1982. Embankment compaction and quality control at James Bay
hydroelectric development. Transportation Research Record 897:
8.15.
15. GARNEAU R., PARÉ J.J., VERMA N.S., CRUICKSHANK D.
1982. Behavior of the LG-4 main dam during construction.
Proceedings of the 35th Canadian Geotechnical Conference,
Montréal, September 28.30. Canadian Geotechnical Society,
Rexdale, Ont., 258.278.
16. VERMA N.S., PARÉ J.J., BONCOMPAIN B., GARNEAU R.,
RATTUE A. 1985. Behaviour of the LG-4 main dam. Proceedings
of the 11th ICSMFE, San Francisco, August 12.16. A.A. Balkema,
Rotterdam, 4: 2049.2054.
17. PARÉ J.J., VERMA N.S., KEIRA H.M.S., MCCONNELL A. D.
1984. Stress-deformation prediction for the LG-4 main dam.
Canadian Geotechnical Journal, 21(2): 213.222.
18. MASSIÉRA M., BONCOMPAIN B., FAKHRI Y., LESSARD G.
1989. Comportement contraintes-déformations du barrage
principal de LG-4. Proceedings of the 42nd Canadian
Geotechnical Conference, Winnipeg, October 23.25. Canadian
Geotechnical Society, Rexdale: 196.207.
19. BONCOMPAIN B., MASSIÉRA M. 1991. Déformation de
noyaux de remblais zonés Durant la construction: influence du
zonage et de la nature des matériaux, Vol. 2. Proceedings of the
44th Canadian Geotechnical Conference, September 29 . October
2. Canadian Geotechnical Society, Rexdale, Ont., 98. 1.98.8.
20. MASSIÉRA M., BONCOMPAIN B., MERHEB-HARB J. 1999.
Interprétation des measures inclinométriques durant la
construction des remblais zonés des ouvrages de retenue du
Complexe La Grande, phase 1. Canadian Geotechnical Journal, 36
(3): 533.543.
21. Seed, H.B. (1980), “Earthquake- Resistance Design of Earth
Dams”, Symposium on Problems and Practice of Dam engineering,
Bangkok, 41-59.
22. Seed, H.B., Wong, R.T., Idriss, I.M., Tokimetsu, K. (1986),
“Moduli and Damping Factors for Dynamic Analysis of Cohesion
less Soils”, Journal of Geotechnical Engineering, Vol. 112, No. 11,
1016-1022.
23. Mir Mohammad Hosseini, S.M., et al., (2003), “Dynamic and
Static Properties of Mixed- Clay as Core Material of the Karkheh
Large Embankment Dam”, Proc. 21?? ICOLD Congress,
Question 83, R. 20, Montreal.
24. Iran Water and Power Resources Development Co., (2001), “The
Summery of First Stage of Karkheh Large Embankment Dam’s
Studies”.
Keywords
Embankment dam, geotechnical parameters,
deformation and stress modeling, stability of dam.